CHECKLIST FOR WATERPROOFING WORKS

CHECKLIST FOR WATERPROOFING WORKS
PROJECT (Autofill by Project Name)
MT SOPHIA1
Reference Nos (Autofill by Form Number)
autofill

Block No.       

Storey No.       

Plot No.       

Hse No.       

Inspection Date
1st       

Time Start        

Time End        

Inspection Date 
2nd        

Time Start        

Time End        

GENERAL

1. materials approved

Contractor’s Rep Inspection

1st

2nd

Description of Non-compliance      

2. shop drawing approved

Contractor’s Rep Inspection

1st

2nd

Description of Non-compliance      

3. incl upturn/penetration

Contractor’s Rep Inspection

1st

2nd

Description of Non-compliance      

SUBSTRATE PREPARATION
4. surface clean and no sharp protrusion

Contractor’s Rep Inspection

1st

2nd

Description of Non-compliance      

5. fillets at wall/floor joints

Contractor’s Rep Inspection

1st

2nd

Description of Non-compliance      

6. door & window frames installed

Contractor’s Rep Inspection

1st

2nd

Description of Non-compliance      

FINAL PREPARATION

7. apply primer if req’d

Contractor’s Rep Inspection

1st

2nd

Description of Non-compliance      

8. thickness of each coat

Contractor’s Rep Inspection

1st

2nd

Description of Non-compliance      

9. lap sufficient

Contractor’s Rep Inspection

1st

2nd

Description of Non-compliance      

10. treatment around pipes

Contractor’s Rep Inspection

1st

2nd

Description of Non-compliance      

11. protective screed

Contractor’s Rep Inspection

1st

2nd

Description of Non-compliance      

12. ponding tests

Contractor’s Rep Inspection

1st

2nd

Description of Non-compliance      

name       

Signature       

Date       

Calculated Waterproofing Area (m2)