Checklist For Tilling

CHECKLIST FOR TILING
PROJECT (Autofill by Project Name)
MT SOPHIA1
Reference Nos (Autofill by Form Number)
autofill

Block No.       

Storey No.       

Plot No.       

Hse No.       

Inspection Date

1st       

Time Start       

Time End       

Inspection Date
2nd       

Time Start       

Time End       

SURFACE PREPARATION

1. shop drawing / layout approved

Contractor’s Rep Inspection

1st

2nd

Description of Non-compliance      

2. Substrate

Contractor’s Rep Inspection

1st

2nd

Description of Non-compliance      

3. Level

Contractor’s Rep Inspection

1st

2nd

Description of Non-compliance      

4. waterproofed

Contractor’s Rep Inspection

1st

2nd

Description of Non-compliance      

5. screed with fall

Contractor’s Rep Inspection

1st

2nd

Description of Non-compliance      

6. door & window frames installed

Contractor’s Rep Inspection

1st

2nd

Description of Non-compliance      

7. services installed

Contractor’s Rep Inspection

1st

2nd

Description of Non-compliance      

TILING

8. Setting out point

Contractor’s Rep Inspection

1st

2nd

Description of Non-compliance      

9. Correct tile & pattern

Contractor’s Rep Inspection

1st

2nd

Description of Non-compliance      

10. Dry lay for approval

Contractor’s Rep Inspection

1st

2nd

Description of Non-compliance      

11. Neat cutting

Contractor’s Rep Inspection

1st

2nd

Description of Non-compliance      

12. Correct grout for pointing

Contractor’s Rep Inspection

1st

2nd

Description of Non-compliance      

13. Straight joints

Contractor’s Rep Inspection

1st

2nd

Description of Non-compliance      

14. evenness

Contractor’s Rep Inspection

1st

2nd

Description of Non-compliance      

15. Marble/stones laid in accordance to tile setting out

Contractor’s Rep Inspection

1st

2nd

Description of Non-compliance      

name      

Signature      

Date      

Calculated Tiling Area (m2)