Image
Please use mobile phone to attach photo
Location of work 施工位置
Machine Operator’s Name 吊车驾驶员姓名
Description of work 工作性质叙述
Piling Machine No. 吊车牌照
Permit validity Period 准证有效期(From)
Safe Working Load 安全负重量
Permit validity Period 准证有效期 (Till)
Piling Work(s) image
Valid LM Certificate available
MOM licensed crane operator available
Approved Examiner test certificate available for Lifting Gears f
Inspection checklist by crane operator & Lifting Supervisor available
Qualified Lifting Supervisor available
PE design available for underpinning, sheet piling, bracing or other means of shoring to support any adjacent structure or with worksite
Piling machine access in good condition
All bored hole properly barricaded
Safe Work Procedure, Risk Assessment and tool box meeting conducted/ briefed to all workers; records maintained
Spreader beam available (for lifting rebar cage) and in safe working condition
Method statement for lifting work available
Lifting Appliances are in good condition
All underground services (e.g. pipe or cables etc.) identified/check by designated person; cable detection drawings available
Sitting distance from overhead electrical cable Min 3 meters and roped off with warning sign
Piling / Lifting area cordoned off
Lifting gear color code system is implemented / followed
Warning signs are displayed at conspicuous location
All necessary PPE provided to work personnel e.g. ear muff, goggles etc…
Qualified Lifting Supervisor, Rigger & Signalmen are present and they are in proper attire
Engineers check on probable soil settlement and any damages induced and affect the surrounding buildings.
Piling operation process supervised by trade supervisor / designated person
Designated person is appointed for the inspection of piling equipment