Checklist For Painting

CHECKLIST FOR PAINTING
PROJECT (Autofill by Project Name)
MT SOPHIA1
Reference Nos (Autofill by Form Number)
autofill

Block No.      

Storey No.      

Plot No.      

Hse No.      

Inspection Date

1st      

Time Start      

Time End      

Inspection Date

2nd      

Time Start      

Time End      

SURFACE PREPARATION

1. substrate cured and dry cracks / holes patched

Contractor’s Rep Inspection

1st

2nd

Description of Non-compliance       

2. surface sanded down / scrapped

Contractor’s Rep Inspection

1st

2nd

Description of Non-compliance       

APPLICATION

3. to manufacturer’s instruction

Contractor’s Rep Inspection

1st

2nd

Description of Non-compliance       

4. check method (spray / roller / brush)

Contractor’s Rep Inspection

1st

2nd

Description of Non-compliance       

5. protection to wall, floor, frames, locks, hinges, etc.

Contractor’s Rep Inspection

1st

2nd

Description of Non-compliance       

SEALER/PRIMER COAT

6. correct type

Contractor’s Rep Inspection

1st

2nd

Description of Non-compliance       

7. evenness / thickness

Contractor’s Rep Inspection

1st

2nd

Description of Non-compliance       

UNDER COAT

8. grouting around frame

Contractor’s Rep Inspection

1st

2nd

Description of Non-compliance       

9. verticality

Contractor’s Rep Inspection

1st

2nd

Description of Non-compliance       

FINSIHING COAT

10. undercoat dried

Contractor’s Rep Inspection

1st

2nd

Description of Non-compliance       

11. even application

Contractor’s Rep Inspection

1st

2nd

Description of Non-compliance       

12. clean up

Contractor’s Rep Inspection

1st

2nd

Description of Non-compliance       

name        

Signature        

Date        

Calculated Painting Area (m2)